EPC Tailings Filtration & Dewatering Plant for Concentrate Lines 5, 6 & 7

Iron oreCompleted

Process view

Tailings filtration & dry stacking

Thickener · Filter press · Dry stacking

Capacity
600 t/h dry solids
Status / progress
Contract completed

Project overview

Full engineering, design and consulting services: review and completion of conceptual engineering, basic and detailed engineering, completion of parts of the existing basic and detailed engineering, procurement engineering, on-site inspection, and issue of construction drawings for the tailings dewatering and filtration unit and its associated components for concentrate lines 5, 6 and 7 (Phase 2) at Gol-e-Gohar, Sirjan.